Last Updated: 9-Mar-2011
Status Priority Category Project / Effort Task Notes / Scope  Owner Start Date Original Target Date Revised Target Date Completion Date
Completed (1) High Festival Festival Web Site Procure festival-only domain name GreekVillageFestival.info Gabriel February 17, 2011 February 24, 2011 March 10, 2011 March 7, 2011
In Progress (2) Medium Festival Festival Web Site Populate festival web site content Placeholder is set up.  Awaiting content Christopoulos, Z.; Gabriel, J.; Hetzer, S. February 17, 2011 March 27, 2011    
In Progress (2) Medium Facilities Fix Alarm Panel Following defiant response by Eastport, Richey has agreed to coordinate a meeting.  We are now awaiting a date. Chris Richey was planning to set up meeting - have not heard back since early December

Do we have a replacement vendor for Eastport?  How do we get this restarted?
Pappas; Xanthos; C. Hetzer August 23, 2009 September 30, 2009    
In Progress (1) High Facilities Complete repair of identified leaks   Efforts underway by Pappas, Fakiris, et al Pappas; Fakiris September 1, 2010 March 15, 2011    
In Progress (1) High Finance Staten Island Sale Schedule Closing H. Raptakis addressing remaining issues with AG, Buyers Gabriel August 31, 2009 September 15, 2009 February 28, 2010  
Not Started (1) High Finance Quarterly cash flow analysis   Following July meeting, we reviewed recommended changes via e-mail. Need to include Projections in order to understand our real financial state.

Date Revised to reflect Oct PC meeting


As part of our ongoing efforts on financial transparency we should include quarterly financials that include not only YTD actuals, but revised projections for remainder of year, which this was intended to accomplish.
Demou; Komoulis; Panagopoulos, Pappas   October 14, 2009 March 31, 2011  
In Progress (1) High Parish Development Stewardship Paradigm Rollout Identify pilot families Very few responses received from working group.  PC should collectively nominate 5 families Patestas; Chaimanis November 1, 2010 December 31, 2010 March 17, 2011  
In Progress (1) High Parish Development Complete Ministry List   Mary & Bill are working on this Patestas; Chaimanis November 1, 2010 December 31, 2010 March 31, 2011  
Not Started (2) Medium By laws Election rules Allow "bullet" voting Recommendation based on feedback from parishioner during 2010 election.  In short, even if we have minimum number of candidates, parishioners should be able to express opinions by voting for subset of candidates. Panagopoulos        
In Progress (2) Medium Facilities Address issues with church cleaning Work with Gus to prepare work schedule Theo has agreed to perform this task.

Is this still an issue?  Who is coordinating?
Pappas; Xanthos; C. Hetzer August 14, 2009 September 10, 2009 October 10, 2009  
In Progress (2) Medium Finance Define & document revised funds disbursement policies   Draft Completed. Still need to review with Effie Marie and with impacted committee chairs
This should probably still be completed in line with our new finance reviews.  Original attempt was never completed.
Demou; Komoulis; Panagopoulos, Pappas March 24, 2009 May 9, 2009    
Not Started (2) Medium Hall Rentals Lighting Prepare plan for lighting improvements PP spoke to Peter Karageorgeo and C&K. We need to speak to Richie about whether we have conduits, viability, cost, etc.
Is this still an issue?  Some tactical improvements were made in late 2009.  Are they sufficient?
Pappas August 14, 2009 September 14, 2009 September 24, 2009  
In Progress (2) Medium Membership Complete Membership Directory   E-mail sent to parish Listserv with June 8th deadline to finalize data

Alex is working on this.  We need to establish hard cut-off date, and to communicate to parishioners.
Ipiotis October 1, 2008 February 1, 2009    
In Progress
Completed?
(2) Medium Misc Update corporate name Determine whether Charlie will provide legal services Is this completely done?   Chicalcos; Hetzer August 1, 2009 September 3, 2009    
In Progress
Completed?
(2) Medium Misc Obtain non-profit mail permit   Do we have our new tax-exempt paperwork? Chicalcos; Hetzer        
Not Started (2) Medium NCD Round 2 Kick-off   Need to agree schedule Brakatselos; Hetzer        
Not Started (2) Medium Parish Development Stewardship Paradigm Rollout Visit pilot families   Patestas; Chaimanis   March 18, 2011 June 30, 2011  
Not Started (1) High PD, Stewardship, Membership Document ALL committee functions & procedures Document procedures for ministry participation We need clear documentation on procedures for handling ministry forms.  This includes who gets copies, who is responisble for distributing these copies and how we track progress on contacting parishioners. Brigis; Chaimanis; Costas; Hetzer; Patestas; Smith; Vandoros March 11, 2011 March 31, 2011    
In Progress (2) Medium Technology Document ALL committee functions & procedures   New Wiki is set up.  JG to send instructions to PC PC Ongoing Ongoing Ongoing  
Not Started (3) Low Finance iGive.com Christmas Campaign   Alex Gratsias had agreed to coordinate publicity/marketing effort as we approach Christmas shopping season. NOTHING HAPPENED - NEED TO FIND COORDINATOR FOR 2011